Hillburn, New York

Re-use of former HTI refrigerant recapture facility. The applicant is repurposing the building for use as a redi-mix concrete manufacturing and distribution facility. All loading and distribution will be within enclosures (either pipe connections or indoors), with air filtration units employed to reduce dust from entering the air. The process also employs water recycling technology to significantly reduce the amount of water used in the concrete manufacturing process. Additions to the building include a raised roof and four storage silos. Required approvals include site plan, special use permit (for an otherwise prohibited use), and height variances.

Planning Board Narrative Summary

Comment and Response Letter

NEGATIVE DECLARATION ISSUED FEBRUARY 25, 2015

SPECIAL USE PERMIT GRANTED FEBRUARY 25, 2015

VARIANCES GRANTED APRIL 29, 2015

FINAL SITE PLAN AND SUBDIVISION APPROVAL GRANTED MAY 21, 2015

 

 